More Info →
×

Current Construction Activity

Latest Activity – Construction Activity Update: April 22, 2014

Cosumnes River College-

  • Construction crews are working on TPSS #11 and 12 ductbank.
  • Crews are installing junction boxes and signal raceway from Old Calvine to the Cosumnes River Boulevard (CRB) bridge.
  • Foundation work is underway in station area.
  • Please note that Lot F will be closed for all parking soon. Please check this website for updates, and stay alert for signage announcing closure dates at Cosumnes River College.

Center Parkway-

  • Wall work continues at Valley Green and along CRB from Center Parkway.
  •  Construction crews are working on the grade beam and underdrain at Center Parkway.

Franklin-

  • The contractor is expected to finish grading the Franklin park-and-ride lot this week.

UPRR-

  • The potholing previously scheduled for this week at Wall E-1 was postponed and may start next week
  • Utility work continues in the UPRR corridor
  • Trenching is taking place for the sound walls. CIDH cages are being set and concrete poured.

Morrison Creek-

  • The week of April 21-25 the contractor will haul dirt on Detroit Boulevard. Approximately 50 trucks per day will be accessing the site via Detroit Boulevard.

Construction work schedule is subject to change due to unforeseen circumstances

View Past Construction Activity


Overview

The Blue Line to CRC project will add four new light rail stations (Morrison Creek, Franklin, Center Parkway and Cosumnes River College), 2,700 park-and-ride spaces and a major new transit center at the Cosumnes River College Station.The Blue Line to CRC light rail extension project (also referred to as South Line Phase 2) is one of the highest priority transit projects in the region and, once completed, will extend light rail 4.3 miles from the existing terminus at Meadowview Road to Cosumnes River College.Construction of the two light rail bridges over Cosumnes River Boulevard and Morrison creek is almost complete. Civil and track work is scheduled to begin in September 2013, with revenue service beginning late 2015. Click here to view a current project map.


Upcoming Events


Civil Construction Underway

Tree Removal Mitigation

Removal of some trees along the alignment of the Blueline to CRC will be necessary to facilitate the construction of the light rail track and stations for this important light rail extension.  Every effort has been made to minimize the number of trees being removed, and replacement trees will be planted along the alignment, the CRC campus and at the new stations as construction is completed.  In fact, RT will be planting 1.6 trees for every tree removed.  To learn more about how tree removal is being mitigated for please view  Chapter Four – Affected Environment in the Final EIR/S. It can be viewed here.